Published 24 November 2026 · 3 min read
If you own an old house or villa in Riyadh and want to demolish it to rebuild or sell a clear plot, the work runs in seven steps: survey, disconnect power and water, get the demolition licence through Balady, fence the site, demolish, remove the debris, then break out foundations, level and hand over. This guide walks through each step from our demolition work in Riyadh and the official requirements as they stood on 24 November 2026; where they differ, the official text applies.
Prepared by Bariq Arabia, a Riyadh contractor and manufacturer certified to ISO 9001, 14001 and 45001, from the official sources and our work on site.
Based on: Demolition licence service, Balady (Arabic) · Construction, demolition and renovation waste disposal requirements, MoMaH (1445 AH, Arabic) (full list at the end)
Step 1: Survey and scope
Before any price or date, the contractor surveys the building to choose the method and plan the site. The main points we record:
- Structure type: concrete frame, load-bearing walls or an older build.
- Number of floors, and any basement, underground tank or septic tank.
- Walls shared with neighbours and adjoining buildings.
- Street and entrance width, which sets the size of equipment.
- Anything to keep: a boundary wall, a tree or part of the building.
- What is inside: doors, windows, AC units, timber and steel.
Step 2: Disconnect power and water
Demolition does not start until services are disconnected. Contact the Saudi Electricity Company (933) to disconnect the supply or remove the meter, and the National Water Company to disconnect water, and ask each for the documents they need; the demolition licence and proof of ownership are often requested.
Remove gas cylinders and fuel tanks, and ask your telephone or fibre provider to disconnect the line. Any live service inside the building is a danger to the crew and the machines.
Step 3: The demolition licence, and who deals with the debris
Demolishing a building needs a licence from the municipality through the Balady platform, applied for by the owner through an engineering office; the published service time is 7 working days at Riyadh Municipality. Demolishing without a licence carries a SAR 10,000 fine per building in Riyadh under the March 2026 penalties schedule.
The Ministry's construction and demolition waste requirements oblige the licence holder to contract a licensed transporter to take all debris to disposal sites set by the municipality, and the engineering office enters the estimated debris quantities in the licence on Balady.
Saudi demolition licence: requirements, documents, time and fineStep 4: Fence and secure the site
The site is fenced before the machines start, so the public and children stay away from the demolition zone. The pavement and street are protected, warning signs go up and an equipment entrance is left wide enough.
The usual temporary fence in Riyadh is white shinko (corrugated sheet), with height and fixing rules by street width.
Shinko temporary site fencing: rules and installationStep 5: The demolition
- Strip out first: doors, windows, AC units and timber, sorting what can be sold or recycled.
- Demolish top-down with an excavator and breaking attachment, spraying water throughout to keep dust down.
- Demolish by hand or with small breakers beside shared walls so the neighbour's building is not damaged.
- Separate steel from concrete as you go, which makes removal easier.
- Work in permitted hours and watch vibration and noise next to occupied buildings.
Step 6: Remove the debris
Debris goes to disposal sites set by the municipality through a licensed transporter, who records the quantities on the construction and demolition waste receipt form. Ask for copies of these forms when the job ends.
Leaving demolition debris behind is a violation; reports on the waste-management violations schedule put the fine for individuals at SAR 5,000 to 20,000. Make sure the demolition quote clearly includes removal.
Step 7: Foundations, levelling and handover
- Break out and remove footings and ground beams if the new design requires it.
- Backfill and level any basement, underground tank or septic tank.
- Level the plot and clear the remaining debris.
- Hand over a plot ready for site preparation and construction.
How long does it take, and what does it cost?
Time and cost vary from building to building. They depend on the area and floors, any basement or tank, shared walls, street width, the volume of debris and the haul distance, and whether you want foundations removed and the plot levelled. So we set the time and price in the quote after the survey, and send a preliminary estimate within 24 hours of receiving photos.
What affects demolition cost, and what to send for a quote